construction challenges for bridges in hilly area pdf
Foundation construction for any large bridge takes time. Problems encountered during construction of foundation depend upon type of foundation, soil strata encountered, equipment/plant deployed and logistic problems. Construction difficulties anticipated during the execution be kept in view while planning the works/ period for the job. Foundation can be opened foundation, pile foundation, well foundation or any other types of foundation.
In case of well foundation, the various type of soil are encountered and it becomes difficult to give any clear time schedule about the sinking of wells unless the soil details are very clear and the anticipated profile matched with the actual encountered. In case of bouldery and clayey soil the rate of sinking schedule is likely to be slow when compared with the sandy soil. Also there may be requirement of pneumatic sinking technique subsequent to open grabbing due to difficulties in sinking of well.
As the cost of pneumatic sinking is very high, this should be deployed judiciously. In such cases, there is need to keep the details of all the sinking difficulties in a systematic order and this can be reviewed in consultation with decision making authority.
Hilly region pose unique problem for bridge construction. In a restricted hilly area itself climatic conditions, geological features and hydrological parameters vary considerably. Keeping in view the bridge site and various constraints, type of bridge and method of construction are to be selected carefully for safe, economical and successful completion of bridge construction.
Various challenges that come across while constructing bridges in hilly area are
1. Construction of bridge across deep gorges
2. Construction of bridge on rivers with bouldary beds
3. Construction of bridges in extreme temperature zones
4. Construction of bridges on sharp turn on highway
5. Landslide or Debris flow
Deep gorges, rivers with bouldary beds, extremely low temperature condition, high winds, landslide etc. in hilly regions require special attention to complete the activities of bridge planning and construction in a systematic way and are discussed here in.