Blackstart and System Restoration Simulationsusing Power World Simulator
#1

Blackstart and System Restoration Simulationsusing Power World
Simulator


[attachment=18087]

Operations Applications
• Blackstart and Restoration Procedure
assessment and review
• System Operator Response Training
• These are two very distinct applications
even though both are related to system
restoration


NERC System Restoration Guidelines
• Consideration should be given to connecting shunt reactor devices to
help stabilize generating units being brought on line.
• Transmission corridors for supplying start-up power should be
identified and switching procedures determined, taking extra care to
isolate damaged facilities.
• Units without blackstart capability should be prepared to begin the
start-up process when start-up power becomes available.
• Transmission system corridors to support the start-up process should
be established but not energized until needed.
• As units with blackstart capability come on line, energize appropriate
transmission system corridors supplying start-up power for units that
are ready to return to service.



PowerWorld Simulator
• Simulator is run in the “Simulation” mode
providing for chronological progression of
load flows as actions are taken on the
system
• Lines are monitored for overloads
• Contouring is used to monitor voltage levels


System Reconstruction
• As the system is reconstructed, the island
swing bus will pick up load.
• Other generation must be dispatched to
keep the swing bus from exceeding its
capacity.
• Load must be added in small steps to
prevent collapse of the system



System Operator Response Training
• Scenarios are created for which no specific
restoration procedure exists.
• There are typically several right and wrong ways
to restore the system
• Operators use NERC and company guidelines to
re-establish load and generation and resynchronize
where necessary
• Additional system events are thrown at the
operators in the course of re-establishing the
system



PowerWorld Simulator as a Power System Simulator
• EMS simulators can be in high demand. PowerWorld
Simulator can serve as a second simulator for certain
scenarios.
• As the use of Retriever in the control room becomes more
widespread, Simulator becomes more valuable in training
operators and engineers in the use of PowerWorld graphics
in real time. Simulator can be used to develop displays,
voltage contouring and line monitoring for Retriever.
• Simulator can be used to identify early warning graphical
“signatures” for potentially damaging events so that these
events can be avoided.
Reply

Important Note..!

If you are not satisfied with above reply ,..Please

ASK HERE

So that we will collect data for you and will made reply to the request....OR try below "QUICK REPLY" box to add a reply to this page
Popular Searches: top 5 ppt on ann based power system restoration, food world management system, abstract for ann based on power system restoration, ann based power system restoration slides, ann power system restoration ppt, ann based power system restoration documenation, ann power system restoration,

[-]
Quick Reply
Message
Type your reply to this message here.

Image Verification
Please enter the text contained within the image into the text box below it. This process is used to prevent automated spam bots.
Image Verification
(case insensitive)

Possibly Related Threads...
Thread Author Replies Views Last Post
  SCADA FOR POWER SYSTEM AUTOMATION seminar paper 3 4,825 05-04-2016, 01:07 PM
Last Post: dhanabhagya
  Advanced Construction Methods for New Nuclear Power Plants seminar details 3 3,112 24-10-2014, 11:40 PM
Last Post: jaseela123d
  Radio frequency based real time Child Monitoring and alarm system simple details seminar addict 1 1,998 06-09-2014, 06:45 PM
Last Post: Guest
  SURATGARH SUPER THERMAL POWER STATION seminar addict 2 2,170 05-09-2014, 10:36 PM
Last Post: seminar report asees
  Hydro power plants PPT seminar details 1 2,230 24-08-2014, 01:09 AM
Last Post: avantidarbhe
  A Modular Single-Phase Power-Factor-Correction Scheme With a Harmonic Filtering seminar details 2 1,921 26-07-2013, 04:44 PM
Last Post: computer topic
  Siemens AG, Power Generation Germany seminar addict 2 2,822 09-04-2013, 10:46 AM
Last Post: computer topic
  power management using load shedding. seminar addict 2 1,957 13-03-2013, 02:44 PM
Last Post: computer idea
  THERMAL POWER PLANT project uploader 1 2,540 18-01-2013, 12:22 PM
Last Post: seminar details
  SOLAR POWER TOWER full report seminar details 1 2,333 30-11-2012, 01:39 PM
Last Post: seminar details

Forum Jump: