The Resource Allocation syndrome: the prime challenge of multi-project management
#1


Presented By:
Anamika Saxena
Aritra Sen
Aniruddha Datar

[attachment=12160]
The Resource Allocation syndrome: the prime challenge of multi-project management
Introduction
In case of Multi-Project Management:
2 research questions:
(1) On a project portfolio-level, are there any operational problems that are general to multi-project management?
(2) If so, which underlying mechanisms of the multi-project setting cause these problems?
Flow of Presentation:
• Two cases were analyzed :
– Signaling systems, contract division
– Telecom operator R&D division
• Common characteristics and differences were observed.
• The common problems and their reasons.
• Solution
Similarities
• Project interdependencies and lack of resources
• Priority setting and resources reallocations
– issues concerning prioritization of projects and the distribution personnel
• Competition between projects
– Due to ambiguous cause–effects relationships, unclear project priorities, and conflicting interests between different projects and departments
• Short term problem solving
– both the steering committees and middle management were occupied with ad hoc problem solving.
– Long-term knowledge development or process improvements, were always subordinated to short-term problem solving in different singular projects.
Consequently, there was a widely spread feeling of inefficiency in both organizations.
• 1. Common multi-project management problem
Resource allocation syndrome.
• This happens when the portfolio management is overwhelmed with issues like:
– Prioritization of projects
– Project personnel transfer
– Search of slack resources.
• This particular problem is common to all multi-project setting independent of project type, size, members or the context.
• But resource re-allocation is not a fruitful solution, it causes more negative effects and forces the management to continuous fire fighting which leads to reactive behavior and short term problem solution.
• 2. The underlying reasons???
1. Causes disturbing resource demand
• Failing project scheduling
• Failing project scheduling
• Centralized resource planning system in both the cases.
• Personnel allocated to different projects w.r.t time schedule and office priorities.
• So, priori planning becomes after-the-fact-prioritization.
• Over commitment
• “Canary cage approach”- by Clark and Wheelwright.
• Without changing the platform technology and any increase in resource availability, more projects are added by management.
2. Causes disturbing resource supply
Management accounting system
• Paying based on engineering hours spent on projects. This is considered as earning to the particular department.
• Department meeting, learning and idle time are considered as costs to the department.
• So incentives for engineering hours only, not for productivity improvement.
• In case of R&D, no available information about personnel and potential efficiency improvement to the management.
• Opportunistic behavior of project managers
• Politics between departments
Conclusion
• It proves that resource allocation syndrome is the common enemy to all multi-project portfolios.
• This problem is not only a planning and scheduling issue, the accounting system, incentive structure, internal politics etc are playing vital role in it.
• Multiple projects handling does not mean to superimpose an extra level of co-ordination on the traditional system and structures, more time and money must be spent on review meetings, new necessary infrastructure .
• The whole system of managerial procedures has to be re-conceptualized from its roots.
Reply

Important Note..!

If you are not satisfied with above reply ,..Please

ASK HERE

So that we will collect data for you and will made reply to the request....OR try below "QUICK REPLY" box to add a reply to this page
Tagged Pages: the resource allocation syndrome the prime challenge of multi project management,
Popular Searches: mercer engineering challenge, steganography using syndrome trellis codes type ppt, c program to determine nth prime number, human powered vehicle challenge, need of prime no, ppt of blue baby syndrome, resource management system project report,

[-]
Quick Reply
Message
Type your reply to this message here.

Image Verification
Please enter the text contained within the image into the text box below it. This process is used to prevent automated spam bots.
Image Verification
(case insensitive)

Possibly Related Threads...
Thread Author Replies Views Last Post
  ERP – Enterprise Resource Planning project report helper 4 4,058 11-02-2012, 03:54 PM
Last Post: seminar paper
  INTERNATIONAL HUMAN RESOURCE MANAGEMENT seminar class 1 2,709 29-08-2011, 12:31 PM
Last Post: smart paper boy
  Competency Approach to Human Resource Management smart paper boy 0 1,847 21-06-2011, 09:27 AM
Last Post: smart paper boy
  project report on working capital management in HAL seminar class 0 3,837 28-02-2011, 11:13 AM
Last Post: seminar class
  Emotional” Project Management seminar class 0 1,337 17-02-2011, 10:34 AM
Last Post: seminar class
  China’s Economic Wonder and its Impact on Resource Consumption project report helper 0 1,584 20-10-2010, 10:02 AM
Last Post: project report helper
Thumbs Down Human Resource Management Computer Science Clay 0 1,538 01-03-2009, 10:29 AM
Last Post: Computer Science Clay
  Human Resource Management System computer science crazy 0 2,233 23-09-2008, 02:11 AM
Last Post: computer science crazy

Forum Jump: