REFRIGERATOR FINLAL ASSEMBLY at GODREJ & BOYCE Pvt. Ltd. MOHALI, PUNJAB
#1


Submitted By:-
Ankuush kumar
Mechanical Deptt.
M.M.E.C Mullana


[attachment=7868]

Introduction

GODREJ Company was established in the year 1897 by Sheth Ardeshir Burjorji Godrej. The very first product of their colossal national establishment was lock. These were developed to perfection by initially experimenting & gradually devising improvement on imported ones.


REFRIGERATOR FINAL ASSEMBLY (RFA)
R.F.A is the designate area where the final assembly of refrigerator is made. All the work is done manually.

Stages in R.F.A:-
Assembly
Common line
Leakage testing
Evacuation section
Charging section
Plug-in & Plug-out section
Defect analysis stage
Final inspection stage

Assembly lines
There are two assembly lines line1 & line2. All the parts( compressor, condenser, door, cabinet ect.) of a refrigerator assembled here. All the work is done manually.

Common line
The working in this section is initiated by merging of refrigerators of line1 and line2 on to the common line, this is generally a machine operated mechanism, the machine used for this purpose is commonly known as “auto merger”.

Other operations on common line
1. Door fitment of line1 refrigerator
2. Handle fitment line1 refrigerator
3. Logo fitment line1 refrigerator

Leakage testing area
leak detection is made by circulating nitrogen gas in to the particular refrigerator, if any signs of leakage is detected( ie. Change in pressore) it is transferred on to the repair area immediately in purpose to avoid any delay in the running procedure.

Evacuation section
Evacuation Section is one of the most important phase in this assembly cycle. In this section the refrigerators are evacuated using vacuum pumps in order to remove air from it ,for the purpose that air contains moisture and the system will not condense under refrigeration pressure thus causing high operating pressure .This process take app. 45min. If there is large no. of refrigerator on the line then loading and unloading of bodies will take place.

Charging section
After all the possible leak testing and proper evacuation the system are passed on to the charging section ,where each system is filled with refrigerant namely CARE30(ISOBUTANE+PROPANE).

Plug-in & plug-out section
In plug-in section the system are given power supply to inspect its working mode. The complete plug-in procedure is of approximately of 20 to 22 min. . This section is also manually done i.e. unloading and loading of the system are done here, so handling should be in a proper manner. This section also comprises of noise testing and cooling testing area where noise detection and cooling temperature of the system are made to be checked respectively. This section ends with the plugging out of system.

Defect analysis stage
In this section all the technical defect are checked. The main defect are
1.High noise
2.High Ampere
3.No cooling
4. High voltage
5.Compressor not working
6.Dent & scratches on the refrigerator body
Defective bodies are taken away from the line and remaining are send to the stage5.

Analysis of Dents and scratches on line
The one and only and also the major problems in affecting the production rate are “Dents And Scratches” on the external body of the system. They actually mean a deformation on the external body of the system due to some reasons. These are not a problem until they are repairable but if not they just turn body of the system to be nothing but scrap.
Dents and scratches are the main problems in any sheet metal operating system unit. They result in a great production loss and a increase in manufacturing cost. According to data found, a single door dent leading to the system rejection causes a loss of about Rs.1200. Dents and scratches are found on side panels, doors and handles covers of the system.

Dents and scratches Analysis methodology:-
My motive was to find the most affected area of dents and scratches. For this I initiated my analysis by marking 25 systems on the line and inspected these systems at each and every stage under the R.F.A cycle.
After going through the following methodology, I have concluded that dents and scratches are mainly formed in the evacuation section, which is mainly due to improper handling of the system due to which there is a great production rate loss and an increase manufacturing cost.



Reply

Important Note..!

If you are not satisfied with above reply ,..Please

ASK HERE

So that we will collect data for you and will made reply to the request....OR try below "QUICK REPLY" box to add a reply to this page
Popular Searches: jqk mcx rejult punjab state lottery, pricing policies of godrej, bearing assembly animation, godrej refrigerator gf 46, repositioning godrej ppt, circuit diagram of godrej refrigerator, project report of punjab tourism website,

[-]
Quick Reply
Message
Type your reply to this message here.

Image Verification
Please enter the text contained within the image into the text box below it. This process is used to prevent automated spam bots.
Image Verification
(case insensitive)

Possibly Related Threads...
Thread Author Replies Views Last Post
  Recruitment and selection procedure in itc limited and hul ltd 1 1,598 13-08-2018, 08:20 AM
Last Post: Alima
  8 candidate quiz buzzer program code in assembly language 0 365 14-03-2018, 02:22 PM
Last Post: Guest
  sanmar engineering technologies ltd online test model question paper 1 757 22-12-2017, 09:27 AM
Last Post: jaseela123d
  12 class cbse project on refrigerator in marketing management 1 960 02-12-2017, 10:54 AM
Last Post: jaseela123d
  bose sigma 984 front amp wiring diagram 1 740 24-10-2017, 11:34 AM
Last Post: jaseela123d
  itc ltd pestle 1 506 30-09-2017, 11:09 AM
Last Post: jaseela123d
  assembly of foot step bearing pdf 1 507 18-09-2017, 12:36 PM
Last Post: jaseela123d
  Senco jwelary abhuson pvt ltd latest news 1 590 13-09-2017, 11:42 AM
Last Post: jaseela123d
  godrej hr policies ppt 1 923 13-09-2017, 09:02 AM
Last Post: jaseela123d
  management principles followed by dabur india ltd 1 777 07-09-2017, 12:04 PM
Last Post: jaseela123d

Forum Jump: