Rapid Environmental Impact Assessment for 600 MW (2 x 300) Coal Based Thermal Power
#1

[attachment=14690]
Rapid Environmental Impact Assessment for 600 MW (2 x 300) Coal Based Thermal Power Plant at Village-Bade Bhandar, District-Raigarh, Chhattisgarh
1.0 Preamble
Power GenerationScenario in India
As per the 5th National Power Plan (2002-2012) prepared by Central Electricity
Authority (CEA) 2,12,000 MW power is required by the end of 11th Plan. Based on the report of
the working group on Power constituted by Planning Commission, a capacity addition of 41,110
MW is targeted in 10th Plan ending in March, 2007, comprising 14,393 MW Hydro, 25,417 MW
Thermal and 1300 MW Nuclear.
The power generation in India is heavily dependent on conventional fuels like coal and
lignite. The share of hydropower capacity has declined from 43.3% in 1970-71 to 39% in 1980-
81. At the end of 8th plan, it has further reduced to 28.26%. The share of coal as fossil fuel is
projected to increase from 60% during 1995-96 to 74% of total energy by 2010.
According to the Ministry of Power, as on July 31, 2007, India has an installed
generation capacity of 135,007 MW approximately. Despite the fact that the economic
liberalization policies of the government, which began in 1992, were designed to fuel growth
across all sectors, the power industry has not grown sufficiently to meet demand.
The gap between the demand, supply of the power has been increasing leading to
increase power shortage. The following Table highlights the deficit over the year
Reply

Important Note..!

If you are not satisfied with above reply ,..Please

ASK HERE

So that we will collect data for you and will made reply to the request....OR try below "QUICK REPLY" box to add a reply to this page
Popular Searches: top 10 netbooks under 300, environmental project on thermal pollution, diagram of a interference suppressor in a front loading washing machine washing machine defy automaid 600 washing machine, 500 600 stator bar ppt, environmental based ppt for mechanical engineerig, coal allocation, mgmt 600 individual assignment,

[-]
Quick Reply
Message
Type your reply to this message here.

Image Verification
Please enter the text contained within the image into the text box below it. This process is used to prevent automated spam bots.
Image Verification
(case insensitive)

Possibly Related Threads...
Thread Author Replies Views Last Post
  someone with pecuniary common vindication or someone who power 0 427 09-09-2019, 06:23 AM
Last Post:
  someone with economic orthodox justification or someone who power 0 568 08-09-2019, 07:20 AM
Last Post:
  TLMs on Nanotechnology in Science, Maths and Environmental Science 0 759 27-01-2019, 10:43 AM
Last Post:
  impact of urbanziation on birds population in cities 0 690 02-12-2018, 02:03 PM
Last Post:
  vijayawada thermal power station internship contact details 0 857 17-10-2018, 11:36 AM
Last Post: Guest
  foot step power generation system wikipedia 0 715 02-10-2018, 12:50 PM
Last Post: Guest
  vijayawada thermal power station internship contact details 1 882 01-10-2018, 04:41 PM
Last Post: Guest
  student internal mark assessment system 3 2,383 29-09-2018, 12:06 PM
Last Post: Guest
  student internal mark assessment system 2 2,235 29-09-2018, 10:40 AM
Last Post: Guest
  power plant engineering by rk hegde pdf 0 2,128 27-09-2018, 09:59 AM
Last Post: Guest

Forum Jump: