pert problems with solutions
#1

A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. The probability that the project can be completed between days 108 and 120 is
a. 0.0227
b. -2.00
c. 0.9773
d. 0.1058
e. 0.4773
Reply

Important Note..!

If you are not satisfied with above reply ,..Please

ASK HERE

So that we will collect data for you and will made reply to the request....OR try below "QUICK REPLY" box to add a reply to this page
Popular Searches: electronic record system pert chart, pert ppt, pert cpm hindi pdf, prison management problems and solutions, definition of pert and cpm pdf for mba, pert cpm civil engineering construction in ppt, seminar report on cpm pert,

[-]
Quick Reply
Message
Type your reply to this message here.

Image Verification
Please enter the text contained within the image into the text box below it. This process is used to prevent automated spam bots.
Image Verification
(case insensitive)

Possibly Related Threads...
Thread Author Replies Views Last Post
  pgecet previous question papers for ece with solutions free download 1 748 11-04-2017, 10:25 AM
Last Post: jaseela123d
  mhada previous exam questions papers with solutions 1 962 28-03-2017, 09:23 AM
Last Post: jaseela123d
  pgecet previous question papers with solutions ece 1 696 27-03-2017, 01:08 PM
Last Post: jaseela123d
  mhada previous exam questions papers with solutions 1 915 23-03-2017, 11:56 AM
Last Post: jaseela123d
  mhada previous exam questions papers with solutions 1 1,112 15-03-2017, 02:36 PM
Last Post: jaseela123d
  pgecet previous question papers with solutions ece 1 729 10-03-2017, 09:45 AM
Last Post: jaseela123d
  solutions of unsolved questions of automatic controls by b c nakra 1 1,096 07-03-2017, 01:12 PM
Last Post: jaseela123d
  mhada previous exam questions papers with solutions 4 1,537 24-02-2017, 12:50 PM
Last Post: jaseela123d
  current problems faced by reliance industries 1 3,568 27-07-2016, 09:56 AM
Last Post: seminar report asees
  a dasgupta solutions pdf 2 1,949 09-06-2016, 04:13 PM
Last Post: dhanabhagya

Forum Jump: