GROUND IMPROVEMENT TECHNIQUES FOR HIGHWAYS full report
#5

[attachment=15355]
1. ABSTRACT:
Ground improvement is the most imaginative field of geotechnical engineering. It is a field in which the engineer forces the ground to adopt the project's requirements, by altering the natural state of the soil, instead of having to alter the design in response to the ground's natural limitations. The results usually include saving in construction cost and reduction of implementation time.
There are number of techniques available for improving the mechanical and engineering properties of the soil. However, each technique has some limitations and suit abilities to get maximum improvement in the soil conditions with minimum effort. Some of the important techniques are discussed in this paper.
To improve the strength of the soils, especially in case of granular type of soils, COMPACTION METHODES are found as best methods among all type of techniques. Based on the mechanism applied for compacting the soil, it is sub divided into different methods like dynamic compaction, blasting, vibro techniques ...etc.These are briefly discussed in this paper.
When there are some limitations encountered for applying the above technique, grouting techniques, stabilization of soil using different admixtures can be adopted effectively which can bring variations in the soil conditions. The various types of above techniques are briefly discussed in this paper.
Finally, recent advancements in ground improving techniques using GEOTEXTILES, ELECTRIC TREATMENT METHODES are also briefly discussed in this paper. These techniques are widely used in these days.
2. INTRODUCTION:
Large civil engineering projects are being executed in all over the country in order to enhance the infrastructure of the country. Infrastructure facilities have to be often built at sites where the soil conditions are not ideal. The insitu soil characteristics of a construction site are different from those desired, and almost always far from ideal for a designed need. With increased urban development, site with favorable foundation conditions became depleted. At times the civil engineer has been forced to construct structures at site selected for reasons other than soil conditions. Thus it is increasingly important for the engineer to know the degree to which soil properties may be improved or other alterations that can be thought of for construction of an intended structure at stipulated site.
If unsuitable soil conditions are encountered at the site of a proposed structure, one of the following four procedures may be adopted to insure satisfactory performance of the structure.
• By pass the unsuitable soil by means of deep foundations extending to a suitable bearing material.
• Redesign the structure and it's foundation for support by the poor soil. This procedure may not be feasible or economical.
• Remove the poor material and either treat it to improve and replace it (or)
substitute for it with a suitable material.
• Treat the soil in place to improve its properties.
Rigid foundations such as piling present a solution but these are often expensive. In such circumstances, ground improvement using different techniques offers a proved and economic solution. At present a variety of soil improvement techniques are available for making soil to bear any type of structure on it and also for mitigation of seismic hazards. The costs of these methods vary widely and the conditions under which they can be used are influenced by nature and proximity of structures and construction facilities.
3. GROUND IMPROVEMENT TECHNIQUES:
On the basis of mechanism by which they improve the engineering properties of soil, the most of common of these can be divided into the following major categories. These are
• Densification techniques.
• Reinforcement techniques.
• Stabilization techniques.
• Miscellaneous methods

Apart from the methods listed above, there are some other simple methods like removal and replacement of soil. In this paper these are discussed first before taking up above techniques.
3.1. REMOVAL AND REPLACEMENT OF SOIL:
One of the oldest and simplest soil improvement methods is to simply excavate the unsuitable soil and replace them with compacted fill. This method is often used when the problem the soil is that it is too loose. In that case, the same soils used to build the fill, except now it has a higher unit weight (because of compaction) and thus has been better engineering properties. This is a common way to remediate problems with collapsible soils.
Removal also may be available option when the excavated soils have other problems, such as contamination or excessive organics, and need to hauled away. This method can be expensive because of the hauling costs and the need for imported soils to replace those that were excavated. It also can be difficult to find a suitable disposal site for the excavated soils.
Removal and replacement is generally practical only above the ground water table. Earthwork operations become more difficult when the soil is very wet, even when the free water pumped out, and thus are generally avoided unless absolutely necessary.
3.2. PRECOMPRESSION OF SOIL:
Another old and simple method of improving soils is to cover them with a temporary surcharge fill as shown in figure. This method is called precompression, preloading, or surcharging. It is especially useful in soft clayey and silty soils because the static weight of the fill causes them to consolidate, thus improving both settlement and strength properties. Once the desired properties have been obtained, the surcharge is removed and construction proceeds on improved site.
Pre-compression has the following advantages
• It requires only conventional equipment earthmoving equipment, which is readily available. No special or proprietary equipment is needed.
• Any grading contractor can perform the work.
• The results can be effectively monitored by using appropriate instrumentation and ground level surveys.
• The method has a long track record of success.
• The cost is comparatively low, so long as soil for preloading is readily available.
However, there also are disadvantages
• The surcharge fill generally must extend horizontally at least 10m beyond the perimeter of the planned construction. This may not possible for confined sites.
• The transport of large quantities of soil onto the sites may not be practical, or may have unacceptable environmental impacts (i.e., dust, noise, traffic) on the adjacent areas.
• The surcharge must remain in place for months or years, thus delay in construction.
Reply

Important Note..!

If you are not satisfied with above reply ,..Please

ASK HERE

So that we will collect data for you and will made reply to the request....OR try below "QUICK REPLY" box to add a reply to this page
Tagged Pages: full report on ground improvement techniques for highway, ground improvement techniques for highways pdf, ground improvement techniques seminar topics, ground improvement techniques seminar ppt, ground improvement technics seminar report, seminar report on ground improvement techniques, ground improvements techniques for highways seminar pdf and ppt,
Popular Searches: seminar report on ground improvement techniques pdf, ground improvement technique, ppt for ground water improvement techniques, ground improvement techniques seminar topics, ground development techniques doc pdf ppt, seminar report on ground improvement techniques for highways free download, ground water improvement techniques viva questions with answers,

[-]
Quick Reply
Message
Type your reply to this message here.

Image Verification
Please enter the text contained within the image into the text box below it. This process is used to prevent automated spam bots.
Image Verification
(case insensitive)

Messages In This Thread
RE: GROUND IMPROVEMENT TECHNIQUES FOR HIGHWAYS full report - by smart paper boy - 18-08-2011, 10:45 AM

Possibly Related Threads...
Thread Author Replies Views Last Post
  New Techniques Of Erosion Control On Hill Roads computer science crazy 7 10,887 16-03-2018, 07:11 PM
Last Post: Guest
  RAINWATER HARVESTING AND ARTIFICIAL RECHARGE TO GROUND WATER full report project report tiger 11 11,861 17-12-2015, 02:13 PM
Last Post: seminar report asees
  New Techniques Of Waste Water Management computer science crazy 9 16,519 18-08-2014, 05:44 AM
Last Post: Guest
  trenchless technology full report project report tiger 17 17,188 11-07-2014, 10:43 PM
Last Post: ahamed fidha
  RAINWATER HARVESTING full report and ppt project topics 11 25,320 27-03-2014, 01:14 AM
Last Post: onkarok9294
  skylights full report computer science technology 4 6,192 02-11-2013, 01:05 PM
Last Post: sac louis vuitton pas cher
  geopolymer concrete full report project report tiger 11 23,201 16-05-2013, 09:34 AM
Last Post: Guest
  green concrete full report project topics 9 37,211 12-03-2013, 12:45 PM
Last Post: computer idea
  global warming full report project report tiger 16 25,636 02-03-2013, 11:58 AM
Last Post: seminar details
  green buildings for quality living full report project report tiger 5 10,240 16-02-2013, 10:44 AM
Last Post: nagarjun ks

Forum Jump: